Wales’ Deputy Minister for Climate Change Written Statement on Menai Suspension Bridge Works

Lee Waters MS, Deputy Minister for Climate Change, has made a Written Statement on the Menai Suspension Bridge Hanger Works (Phase 2) – Trial.

image: for illustration – By Reading Tom from Reading, UK – The Menai Suspension Bridge, CC BY 2.0

… methodology must be tested before we can finalise the project programme…

The Welsh Government writes:

In October last year the Menai Suspension Bridge was closed to all traffic after a structural concern was identified by engineers.

It was reopened to 7.5T vehicles earlier this month after temporary works were completed, but further work must be delivered before the bridge can be reopened to all traffic.

In this final phase of the programme, all the hangers on the bridge will be replaced.

A preferred method of working has been identified that will minimise further disruption, but this methodology must be tested before we can finalise the project programme.

This means we will need to temporarily close a lane on the bridge to allow engineers to work safely and test the proposed hanger replacement system.

When a lane is closed, traffic lights will operate part time at each end of the bridge – allowing vehicles to cross in either direction when permitted. The trial will commence on the 6 March and is planned to be completed within four days, though this could take longer if there is severe weather or another unforeseeable setback.

Every effort has been made to minimise disruption in the local area and traffic lights will only be in use between Monday and Thursday, and between the hours of 9am to 3pm.

Further updates will be provided once the hanger replacement programme has been finalised…..

Read more….